Details
Project Details
Client
Local Authority
Completion
Summer 2025
Project Value
Circa £1.2m
Duration
14 Weeks
Overview
Project Overview
KPS delivered a £1.2 million roofing replacement programme across three Surrey schools over 14 weeks. The works were completed on time, within the agreed budgets and with zero reportable incidents, while teaching and day-to-day school operations continued
Challenges
Coordinating Roofing Works Across Three Live School Sites
KPS Ltd was appointed through its framework with Surrey County Council to deliver a multidisciplinary roofing programme across three schools.
with works delivered during the summer and autumn terms.
Refurbishment
Comprehensive Roofing Replacement and Upgrades
Some key highlights of the projects were:
Over 1000lm of complex Scaffolding installed across the 3nr sites, including electric hoisting for each site, installed by our NASC approved Scaffolding Contractor.
Approx 2000sqm of Tapered Insulation & Felt Overlay System to the roofs at the 3nr Schools.
Over 500sqm of Tiled Roofing Systems on Tadworth including New Tyvek VCL, Uprated Batten, and Redland Tiles.
52nr Dual Layer Polycarbonate Rooflights in accordance with Langley Roofing Specification.
Zero Reportable Incidents during the project.
Installation
Managing Live School Sites and Unexpected Challenges
of their schools and pupils
FIRE SAFETY & COMPLIANCE
Resolving Fire Safety Challenges with Specialist Expertise