Details
Project Details
Client
Completion
September 2026
Project Value
Duration
6 Weeks
Overview
Project Overview
Refurbishment
Scope of Works
Emergency Lighting Survey and Remedial Works
- An emergency lighting survey was undertaken throughout the school to assess the existing installation and identify any areas requiring improvement or remedial attention.
- Following the survey, additional works were identified and instructed. These were subsequently carried out and completed within the agreed timescales, helping to improve the school’s emergency lighting provision.
Fire Door Survey and Remedial Works
- A comprehensive fire door survey was undertaken, covering approximately 90 fire doors throughout the school.
- The survey identified multiple defects and areas of non compliance requiring remedial attention. Following the findings, the necessary corrective works were undertaken across all identified doors, with the remedial programme successfully completed on time.
Firestopping Works
- A substantial firestopping package was also undertaken as part of the project.
- The works involved addressing firestopping requirements throughout the school, ensuring that identified penetrations and gaps within fire-resisting construction were appropriately sealed to help maintain the integrity of the building’s fire compartmentation.
- The package required careful coordination and management to ensure that the necessary works were completed to the required standards and within the overall project programme.
- This formed a significant element of the project, demonstrating our experience in delivering specialist passive fire protection works within an operational educational environment.
Internal Decoration Works
- Redecoration works were carried out to all school toilet facilities and the main dining hall.
- The works involved preparation and redecoration to refresh these high-use areas, improving their overall appearance and providing durable finishes suitable for a busy educational environment.
External Safety Slab Works
- Additional external works were also undertaken to address hazardous paving slabs in designated areas around the school.
- These works involved rectifying identified trip hazards and improving the safety of external pedestrian areas for pupils, staff and visitors.
Challenges
Challenges
Working within an educational environment required careful coordination and planning to ensure that all works were undertaken safely and with minimal disruption to the school’s daily operations.
We prioritised fire safety and emergency lighting, promptly addressing defects identified in the initial surveys.
The additional remedial requirements identified during the survey process also required effective management of resources and coordination to ensure that the expanded scope was delivered within the required timescales.
COMPLETION
Outcome
The project delivered improvements to the school’s fire safety provisions, refreshed key internal facilities and addressed external pedestrian safety hazards.
This project demonstrates our ability to undertake building compliance surveys, identify and manage additional remedial requirements, and deliver a varied package of maintenance and refurbishment works within an operational educational environment.