Egerton Ward Staff Room, Lobby & WC Refurbishment

Details

Project Details

Location

Conquest Hospital, Egerton Ward, Hastings, TN37 7RD

Client

East Sussex Healthcare NHS Trust

Project Value

Sub £250k

Start Date

09/03/2026

Completion

02/04/2026

Principal Contractor

Knightsbridge Property Services

Overview

Works Overview

The refurbishment and upgrade work to the Egerton Ward staff room, associated lobby, and WC facilities have been completed in accordance with the project specification, approved construction drawings, and hospital operational requirements.

The objective of the project was to improve staff welfare facilities through refurbishment of existing areas, replacement of worn finishes and fittings, upgrade of sanitary facilities, and installation of new fixtures, fittings, and services while maintaining compliance with healthcare standards.

All works were undertaken within a live hospital environment with measures implemented to minimise disruption to staff, patients, and adjacent ward operations.

Refurbishment

Scope of Works

Strip Out & Preparation

The existing staff room, lobby, and WC areas were isolated and prepared prior to commencement of refurbishment works. Existing finishes, fixtures, fittings, sanitaryware, flooring, ceiling elements, and redundant services were removed as required under the project scope.

Waste materials generated during strip-out were removed from site via agreed hospital routes and disposed of at licensed waste disposal facilities.

Builder’s Works

Associated builder’s works were completed including making good existing wall, floor, and ceiling surfaces following removal works and service modifications.

A new window opening was formed in accordance with structural requirements, with installation of a replacement window unit to match the existing building façade and internal finish requirements.

Partitions, Joinery & Fixtures

New IPS units, sanitary partitions, and associated boxing works were installed to WC areas. Joinery installation included:

New base and wall cabinetry

Worktops and upstands

Built-in bench seating

Shelving and storage units

Sink units and associated splashback details

All joinery was installed, aligned, and finished in accordance with project drawings and manufacturer guidance.

Flooring Works

New vinyl flooring was installed throughout designated areas including staff room and WC facilities. Floor finishes included:

Preparation of subfloor surfaces

Application of smoothing compounds where required

Installation of sheet vinyl flooring

Formed cap and cove skirting details to perimeter areas for hygiene compliance

Flooring was sealed and finished in accordance with manufacturer recommendations.

Ceiling Works

Ceiling refurbishment works were completed including replacement and upgrade of suspended ceiling systems where identified.

Works included:

  • Installation of new MF ceiling components where required
  • New ceiling tiles
  • Associated making good around service penetrations and fittings

Decoration

Internal decoration works were completed throughout refurbished areas.

Decoration works included:

  • Surface preparation
  • Filling and making good
  • Application of mist coats, primers, and finish coats to walls, ceilings, and timber surfaces as required

All finishes were completed to project specification.

Plumbing & Sanitary Installations

New sanitaryware and associated plumbing installations were completed including:

Wash hand basins

WC fittings and accessories

Sink installations

Taps and wastes

Drainage modifications and final connections

Associated testing and commissioning were completed following installation.

Mechanical & Electrical Works

Mechanical and electrical modifications and upgrades were completed to support the refurbished spaces. Works included:

Lighting alterations/upgrades
Small power modifications
Fire alarm adjustments
Ventilation modifications
Containment and associated service adaptations

Final testing and certification were completed for all applicable installations.

Water Safety & Validation

In line with healthcare requirements, water hygiene controls were completed including:

  • System flushing
  • Temperature checks
  • Chlorination/disinfection where applicable
  • Legionella compliance checks
  • Pseudomonas sampling/testing where required under project scope