Commercial Refurbishment, Fit Out & Specialist...

Harris Academy Beckenham

Details

Project Details

Location

Harris Academy Beckenham, Manor Way, Beckenham BR3 3SJ

Client

Harris Federation

Project Value

£250k+

Overview

Project Overview

Harris Academy Beckenham appointed KPS to refurbish its sports hall and boys' and girls' changing rooms. The works were programmed for the summer holiday period so that the facilities were ready for the new academic year, on a school that remained occupied around the work area.
The existing sports hall floor was damaged with damp within its build-up and was unsuitable for retention. The changing rooms were dated, with worn floor finishes, a tired suspended ceiling and shower areas that no longer suited how the space was used.

Refurbishment

Scope of Works

Sports Hall

  • Full strip-out and disposal of the existing floor construction (about 908m²), including the rubber finish, shock pads and timber sub-structure, down to the structural slab.
  • Supply and installation of a completely new sports hall flooring system, with perimeter details and multi-sport court line markings.
  • Redecoration of the sports hall walls (about 391m²) as an approved variation.

Locker Rooms, Changing Rooms and Entrance

  • Removal of existing floor finishes, repair and preparation of the subfloor, and installation of new slip-resistant vinyl flooring with coved skirtings.
  • Removal of the suspended grid ceilings and installation of new ceilings with new LED lighting.
  • Strip-out and reconfiguration of the shower areas to create more locker space, with the associated alterations to services.
  • Refurbishment of the toilet facilities, new sanitaryware and cubicles, and wall preparation and decoration.
  • Replacement of fire doors, approved as a variation.

Challenges

Challenges

Damp sub-floor : The slab was assessed for moisture once the old floor was lifted, and the damp-proof membrane was designed and installed to suit the findings before any new flooring went down.

Fixed holiday window : Works were sequenced across the sports hall and changing rooms so that trades could follow each other without delay, with progress and site updates sent to the Contract Administrator throughout.

Fire door delivery : Additional labour and extended working hours were arranged to complete the fire door installations and finishing trades for handover.

Occupied site : Site compound, parking, deliveries and access were agreed with the Academy in advance to keep disruption to the school to a minimum.

COMPLETION

Outcome

The Academy now has a refurbished sports hall with a new sports floor and freshly decorated walls, and modernised changing rooms with new flooring, ceilings, lighting, doors and facilities. The new damp-proof membrane addresses the moisture issue that affected the previous floor.