Details
Project Details
Client
Mitie
Completion
March 2026
Project Value
Sub £250k
Duration
12 Weeks
Description
Description of Works
- To carry out a site set up – barriers and signage
Set up a safe working area - To remove and relocate the loose furniture for each room covering the 640 sq m areas
- Please note – Any fixed items will remain fixed
Uplift and dispose of existing flooring – approx. 640 sq m - Altro / Gerflor / Carpet Tiles
- Mechanically remove any loose adhesive/latex
- Apply 2cts primer
- Apply 5mm latex
- Supply and install Altro Walkway flat lay with welded seams
- Supply and install gerflor flooring as per drawing
- Supply and lay carpet tiles as per drawing
- Supply and install new threshold strips where required
- Apply clear mastic where required
- To carry out making good on completion – flooring replacement works only
- To supply and install 23 nr floor boxes
- To carry out the removal of 3 nr floor boxes that are covered
- To fully test and certificate on completion
- To leave the working area clean and tidy