Commercial Refurbishment, Fit Out & Specialist...

Surrey County Council, Woodhatch Headquarters Welfare Upgrade

Details

Project Details

Location

Woodhatch Headquarters, Reigate

Client

Surrey County Council

Completion

TBC

Project Value

Under £250,000

Sector

Government / Public Sector / Commercial

Duration

12 Weeks

Environment

Occupied local authority headquarters

Overview

Project Overview

KPS was appointed by Surrey County Council to deliver welfare upgrade works at Woodhatch Headquarters in Reigate.

The project involved the refurbishment and upgrade of toilet facilities and tea points across multiple floors, improving dated and failing areas of the building while supporting compliance, accessibility and day-to-day usability for building users.

Challenges

The Challenge

The works were delivered within an occupied local authority headquarters, meaning disruption needed to be carefully controlled throughout the programme.
Several areas of the building were dated or had failing services, requiring a coordinated strip-out and upgrade approach. Due to the nature of the environment, works were staged and completed out of hours wherever required to minimise disruption to building users.

Refurbishment

Scope of Works

The project was delivered across two phases, covering ground and first floor tea points, second floor toilets and first floor toilet facilities.

Phase 1, Tea Point Upgrades

The first phase focused on upgrading the ground and first floor tea points in line with the Surrey County Council design specification.
Strip-out of existing services and fixtures
New kitchen cupboards
DDA compliant rise and fall worktops
Tiling works
Decoration works
Mechanical and electrical upgrades

Phase 2, Toilet Refurbishment

The second phase involved the strip-out and refurbishment of the first floor toilets, alongside adaptations to create improved accessible facilities.
New partitions
Tiling works
Flooring works
Decoration works
SGL cubicle systems
New sanitary ware
Creation of compliant disabled toilet facilities
Creation of ambulant toilet facilities
New lighting
Disabled alarm systems
Automatic door installation for the DDA toilet

Installation

Out-of-Hours Delivery

Because Woodhatch Headquarters remained in use throughout the project, KPS planned the works to reduce disruption to staff and building users.
Out-of-hours working was used as the most appropriate delivery method, allowing the works to progress efficiently while maintaining the day-to-day operation of the building.

Coordination

Improving Accessibility and Usability

A key part of the project was improving accessibility and creating more compliant facilities for all building users.

The installation of DDA compliant rise and fall worktops, disabled toilet facilities, ambulant toilet provision, disabled alarm systems and automatic door access helped bring the welfare areas up to a more suitable standard for the building’s users.

Result

The Result

The completed works delivered upgraded welfare facilities across Woodhatch Headquarters, improving both the appearance and functionality of the toilets and tea points.
Through phased delivery and out-of-hours working, KPS was able to complete the upgrade works while minimising disruption within the occupied local authority building.

CALL TO ACTION

Planning Welfare or Office Refurbishment Works?

If you are planning welfare upgrades, toilet refurbishments, tea point improvements or wider office refurbishment works within an occupied building, KPS can provide the planning and coordination needed to deliver the project properly.