Tollgate Primary School, Summer Structural Works

Details

Project Details

Location

Tollgate Primary School, East London

Client

Boleyn School Trust

Completion

August 2021

Project Value

Under £250,000

Sector

Education

Duration

6 Weeks

Environment

School summer works programme

Overview

Project Overview

KPS  partnered with the Boleyn School Trust for the third consecutive year to deliver summer works at Tollgate Primary School in East London.

The project focused on structural repairs to classroom flooring following a survey that identified timber rot, failed wall ties and health and safety concerns. KPS carried out the works during the school summer break, ensuring classrooms were ready for pupils to return at the start of term.

Challenges

The Challenge

The project followed temporary repair works carried out by KPS the previous year, when structural concerns were first identified within several classrooms.

Many of the timber joists had deteriorated, and ties to the external walls had rusted and failed, creating significant health and safety risks. The 2021 summer programme required a full strip-out and structural repair package within a short school holiday window.

Refurbishment

Scope of Works

The works included structural repairs, drainage improvements and lifecycle upgrades within the affected classroom areas.

Key Works Included

Full strip-out of affected classrooms

Removal of existing flooring substrates

Access to structural timbers

Timber repair works

Installation of new timbers and bracing

Works to meet structural surveyor recommendations

External channel drainage installation

Full classroom redecoration

Woodwork updates to new school colours

Heavy-duty carpet installation

Vinyl installation to kitchenette and wash station areas

Classroom lifecycle upgrades

Installation

Programme-Critical Education Delivery

As with many school projects, programme certainty was critical. The works needed to be completed within the summer break so that classrooms could be handed back ready for the start of term.

KPS planned and delivered the works within the allotted timeframe, ensuring the areas were safe, functional and fit for purpose before pupils returned.

Coordination

Preventing Future Issues

Alongside the structural repairs, KPS installed new external channel drainage to help remove water from the wall line and reduce the risk of future water ingress and timber deterioration.

This approach helped address both the immediate structural concerns and the underlying conditions that had contributed to the issue.

Result

The Result

The works were completed within the school holiday period, allowing the classrooms to reopen safely for the start of the next term.
The completed project provided structurally improved classrooms, refreshed internal finishes and practical drainage improvements to help protect the building moving forward.